QA Project reroofing the Llandinam Building, a laboratory on Aberystwyth University's Penglais Campus:
Multiple factors problematised the successful waterproofing of this laboratory refurbishment, including issues with keeping the building itself waterproof while the works progressed.
The laboratory roof has a series of higher levels draining into central chute outlets and discharging onto lower level roofs. These lower roofs…

This wraparound roof in Talybont in Ceredigion, West Wales, was badly leaking and in desperate need of repair and refurbishment. Water was pooling everywhere, the existing surface was ripped, lifting and leaking, and moss had formed in clumps over much of the surface.
Despite this, the underlying roof was still sound and able to be reused!
After cleaning, stripping back and pressure washing the roof, the decayed felt substrate…
Aberystwyth, on the wet and windy west coast of Wales, is a place that knows how important waterproofing is! Balconies that pool and collect water are balconies that rot and decay before their time, never lasting as long as their materials would suggest. The polymer system, which reuses plastic polymer particles, keeping them out of rivers and seas, is fully waterproof. It provides a seamless, jointless covering for balconies, roofs and…
Knowing the polymer system's flexibility and our high standard of work, Aberystwyth University in West Wales asked us to solve a tricky skylight issue...
Flashings and kerb upstands tend to be manufactured to particular sizes, meaning that non-standard skylights made to special size requirements can often present a challenge.
From working with us before, they already knew that the polymer system adapts comfortably to…

The roof of the Ceredigion Training Centre at Llanbadarn on the outskirts of Aberystwyth was in dire need of proper insulation. The existing roof did not conform to government U-values and the cold roof was costing the training centre money in heating.
We worked with the existing mastic asphalt roof, saving time, money and resources. The entire area was cleaned, with increased ply fascias fitted in preparation for the roof to…

This flat roof in Barry in the Vale of Glamorgan was in need of refurbishment as its existing single ply membrane was leaking. With the high winds and rain of Autumn and Winter 2015, this was causing problems for the owners, who needed to find a lasting solution quickly.
We over-coated the roof with a jointless, seamless liquid membrane system which would wholly prevent any further leakage or water ingress, saving electro testing, as…